Moving a change set version to a different activity
In a ClearCase® UCM project, use the Select Activity dialog to move an element version from the change set of one activity to a different activity.
Procedure
To move a change set version to a different activity:
- Use the ClearCase® UCM Activities view to select the activity whose change set contains the version you want to move. Expand the activity node to display the elements in the change set.
- Expand the element node to display the element versions.
- Right-click the element version that you want to move and then choose Move to Activity from the context menu. The Select Activity dialog opens.
- Select an activity from the list and then click OK.