Order processing

Order processing refers to managing the order after it is captured and until it is fulfilled. A store can be implemented with or without Available-to-Promise (ATP) inventory capabilities.

Order processing typeDescription
Order processing with ATPATP capability predicts the future inventory based on expected inventory receipts, and to estimate future ship dates for back orders. With ATP capability, WebSphere Commerce is able not only to capture an order, but also to process the order and release it to fulfillment. The ATP capability allows the store to verify available inventory quantities and displays an expected shipment date. Therefore, the store is able to provide availability dates not only for inventory in stock but for inventory that is not received. It allows for multiple release dates within 1 order.
Order processing without ATPWithout use of ATP inventory, WebSphere Commerce order processing is limited to ensuring that the item is in stock, and authorizing payment.

Orders are processed with one of the following methods:

  • As single orders that have one order ID and that are shipped only when the fulfillment is completed for each order item (ship-as-complete functionality). Therefore, if the 'ship when complete' option is selected, the order is shipped when all order items are available. If 'ship when complete' is not selected, the available order items are shipped, and the other order items are shipped when they are available.
  • Are orders that are shipped before fulfillment are complete (when complete=false).
The subsets of the order are called releases. Releases group order items that have the following attributes in common:
  • Fulfillment center
  • Order item availability date
  • Ship date
  • Shipping carrier
  • Shipment method
  • Shipping address

Implementing order processing requires the use of ATP inventory capabilities. This new ordering capability also allows customers to specify a date in the future when they want order items to be shipped. The orders that result are called future orders.

A shopper can request expedited handling for certain order items. Because these order items have a different handling method from non-expedited order items, a separate release is created. The pick packer can also request that pick batches be created for all order releases. In this case, expedited order releases are placed in the beginning of the list of releases. Items that are expedited are indicated in the generated pick and packing slips. A store developer can also configure the store to include in the expedited release any non-expedited items in the same order that are available at the same fulfillment center and have the same shipping address.

A store processes payments by using Payment Rule processing. The Payment Rule subcomponent determines what types of payment actions to run at specific times or business events in the lifecycle of an order or the return of a purchase. When a request for a payment action occurs, the payment rule that applies to the request is checked and the appropriate payment actions are taken. For example, the store could be configured to approve payment, make a deposit, or do nothing when the buyer specifies a credit card for payment. In other words, each method of payment has its own set of rules for processing payments, which the developer can configure to the needs of the store processes.

An example of releases

The following charts illustrate how one order is organized into various releases. In this example, the customer wants to send some clothing to his home in Boston, some office items to a district office in Atlanta, and some gifts to his niece and nephew in Orlando. Some of the order items have to be backordered. The customer has also requested some of the items to be expedited, and some of the shipment to be shipped at a future date. One order item has a special shipping carrier due to its larger size and weight.

Date of order: 07 February
Qty Order item Ship address Ship method Ship date Expedite?
3 Dress shirt, white Boston Shipping company Backorder Yes
1 Belt, black leather Boston Shipping company Now Yes
4 Undershirt, V-neck Boston Shipping company Now No
1 File cabinet, 4-drawer Atlanta Ground Now No
1 Waste basket, office Atlanta Shipping company Now No
1 Candy Valentine Orlando US Post Now Yes
1 Video game: Zapper3 Orlando US Post Now No
1 Science kit, child's Orlando US Post 22 April No

By the time the order is fulfilled and closed, eight separate releases are created. Even though all the clothing items are going to Boston, each order item is separated into a release (A, B, and C). The dress shirts were temporarily out of inventory and had to be backordered, so their ship date was different from other items that go to Boston. And the belt was expedited and shipped with priority, so the shipment date was sooner than that of the undershirts.

The order items that go to Atlanta were divided into two releases (D and E), each item shipping at the same time, but with different shipping carriers.

The order items that go to Orlando were divided into three releases (F, G, and H). The customer wanted to get the Valentine's candy to his niece and nephew in time for Valentine's Day (February 14) so he requested expedited shipping. The video game for his niece was not expedited (her birthday is in March) so it was shipped a few days later. The customer requested that the science kit be shipped in the future (his nephew's birthday is early in May), so the kit was shipped much later than the other items, creating an additional release.

Release A

3 Dress shirt, white

shipped to Boston

on 21 February

using Shipping company

Priority

Release B

1 Belt, black leather

shipped to Boston

on 08 February

using Shipping company

Priority

Release C

4 Undershirts, V-neck

shipped to Boston

on 10 February

using Shipping company

Standard

Release D

1 File cabinet, 4-drawer

shipped to Atlanta

on 10 February

using delivery truck

Release E

1 Waste basket, office

shipped to Atlanta

on 10 February

using Shipping company

Release F

2 Candy valentines

shipped to Orlando

on 08 February

using US Post Priority

Release G

1 Video game: Zapper3

shipped to Orlando

on 10 February

using US Post

Release H

1 Science kit, child's

shipped to Orlando

on 22 April

using US Post

With order processing, it is possible to configure the fulfillment process so that an expedited release could also contain any non-expedited order items that are ready to ship when expedited items are shipping. The two releases would have to share all common attributes except ship date and shipping method (expedited or non-expedited). In this example, if the store was configured to combine expedited items and non-expedited items into one shipment, releases B and C could be combined and shipped together if the undershirts were ready to ship when the belt was shipping. Again, releases F and G could also be combined and shipped together if the video game was ready to ship when the candy was shipping. In both instances, the order items can be combined into one release only because they have the same fulfillment center, the same shipping carrier, and the same order item availability date.