Verifying workload submission
Now verify that HCL Workload Automation for Z can submit work and that the work is sent to the correct destination.
Use the following procedure for the controlling system:
- Create a workstation description, leave the destination field blank. This means that operations will be submitted to the system where the Z controller is started.
- Create an application description. Define at least one operation on the workstation you
have created. Submit a daily planning extend or replan batch job to include the new
workstation in the current plan.
Add an occurrence of this application to the current plan.
- Verify that the operations run successfully on this system and that they are reported as complete in the current plan.
- Check that submit events are created in the event data set for the controlling system (for details, see Verifying job submission).
If you have controlled HCL Workload Automation for Z systems in your
configuration, use he following procedure to check that work is sent to these destinations, is
submitted, and that events are returned to the Z controller:
- Create a workstation description for each destination. In the destination field, specify the XCF member name of the tracker, the tracker VTAM® application ID, or the tracker TCP/IP destination name, depending on the type of connection.
- Add an application occurrence to the current plan with operations defined on each of the workstations.
- Verify that the operations run successfully on the correct system and that they are reported as complete in the current plan.
- Check that submit events are created in the event data set for each controlled system (see Verifying job submission).