Using in-effect/out-of-effect dates
You can use run cycles that have in-effect/out-of-effect dates to cause an automatic change after a certain date, such as changing the frequency of an application from daily to weekly, as shown in Using in-effect dates to switch between run cycles.
EQQAMRPL ------------------------ RUN CYCLES --------------------- ROW 1 OF 5
Command ===> Scroll ===> PAGE
Enter/Change data in the rows, and/or enter any of the following
row commands:
I(nn) - Insert, R(nn),RR(nn) - Repeat, D(nn),DD - Delete
S - Specify run days
Application : SAMPLEA An application_desc
In Out of
Row Period name Input Deadline F day effect Effect
cmd Text HH.MM day HH.MM Type rule YY/MM/
DD YY/MM/DD Variable table
'' DAILY___ 21.01 01 08.00 N 4 97/01/
01 97/06/30 JOBCARD_________
business inventory, run every day___
'' WEEK___ 21.01 01 08.00 N 4 97/07/
01 71/12/31 JOBCARD_________
business inventory, run every week__