Select option 7 CRITICAL JOBS to display
the list of jobs in the current plan that are defined as targets of
critical paths. The SELECTING CRITICAL JOBS (EQQSOCJF) panel is displayed
for you to specify the filter criteria for the list. After making
your selections, press Enter to display the BROWSING CRITICAL JOB
panel.
The Risk Level (RL) field can have one of the following
values:
H
High risk. According to the current estimated end time
or to the value specified for JTOPTS(RISKCONFIDENCE), if any, the
job will not complete by the defined deadline. For example, the estimated
end time is later than the deadline or the confidence value is lower
than the value set for the JTOPTS(RISKCONFIDENCE).
When JTOPTS(RISKCONFIDENCE)
is specified, the only condition that causes the high risk level for
a critical job is that the confidence value gets lower than the RISKCONFIDENCE
value.
P
Potential risk. One or more of the critical job predecessors are
late, long running, or ended in error.
N
None. No problem was detected in the network of the critical job
predecessors.
The Recalculation (R) field shows the cause of the
recalculation; it can have one of the following values:
C
Job on critical path, completed or removed for the hot list
D
Dynamic updates to the plan
L
Late job
P
Daily planning
Enter the right scroll command to scroll the list
right:
Enter the S row command to display the list of
jobs belonging to the critical path for the target you selected. The
BROWSING CRITICAL PATH panel is displayed: You can scroll the list left and right by entering the left
and right scroll commands, respectively.
For a critical job with high or potential risk, you
can display a list of the critical job predecessors that are late,
long running, or ended with an error, by entering the critical hot
list command on the BROWSING CRITICAL JOBS panel.