Importing data in view responses
Application Owners can use an Import Data operation on the View Responses page to import spreadsheet data into their application. This can provide a quick start method for adding many records/rows of data into an application from an existing spreadsheet.
The import operation is available for application Owners to use as an alternative to keying each row of data into the Launch experience of their Domino Leap application and as an alternative to using the Data Access Rest API to programmatically add the data.
- When using other spreadsheet tools, save the spreadsheet file into one to the supported formats before attempting to import your data.
- Only spreadsheet data on the active sheet can be imported.
- Each column header must include the ID of the item within your application where the data is mapped.
- An item's ID can be found in the Properties panel when editing the application.
- Imports respect the access settings that are configured within the application, so the application owner must be included in the list of people in the Initiator role.
- The application must not be configured to Limit to single submission per Authenticated User.
- The application must be deployed and not stopped.
- Custom JavaScript added to the applications UI is not run during data import.
- Some data elements, including dates and times, need to be in a specific format to import successfully. To identify the correct input format, it can be helpful to add a record of data using the application Launch UI, and then exporting the row from View Responses and review the output format.
Table data and Attachments can not be imported.
- Use commas to separate the selected choices.
- In cases where one of the selected choices contains a comma, the following sequence can be used as an alternative separator: __#__
The data import operation stops when it encounters blank columns or rows in the spreadsheet.
The data import operation supports a maximum of 1000 rows of data.
- You must replace the column header label with the item IDs required for mapping.
- The metadata can not be imported and must be removed from the spreadsheet or mapped to a form item.
Stage transition emails configured in your application will be sent, so depending on the nature of the emails and the number of records being imported, application owners may want to disable the stage action email associated with the Start stage prior to running the import operation.
- Select one or two rows or spreadsheet data to import as an initial test to help ensure the mapping is set up as expected and the data types are compatible. Review the imported data in View Responses after the import to see that it imported as expected.
- To quickly remove all data from an application, on the Manage page, choose to Export your application without including submitted data and then choose to Upgrade your application and select the option to Replace submitted data.
- Prior to performing a large bulk data import into an application that already has submitted data, creating a backup of the application and all existing records is recommended. On the Manage page, select the Export operation for your application and be sure to select the option to Include submitted data. This will provide an archive of the application and data in the state it was in just prior to the import.