To synchronize a view

About this task

To synchronize a view with a new stream configuration (for example, after a component has been added to the stream), use the following procedure.

Procedure

  1. In the Project Explorer, select the stream (for example, a stream that contains a component that has been added), and click File > Properties.
  2. Click the Views tab. Then select the view and click Properties.
  3. On the General page, click Synchronize with stream.