rerun
You can use the rerun command to rerun a job.
Overview
SUCC
or
FAIL
or ABEND
state. When you submit the
command, the rerun of the job is placed in the same job stream as the original job
and all the associated dependencies of the original job are added. If you rerun a
job that is scheduled to run multiple times, the rerun is scheduled to launch at the
same rate as original job.
Syntax and command line options
ocli plan <rerun | rr> jobselect<[;from=[[folder/]wkstat#]job[at=time][pri=pri]|[streamlogon|logon=new_logon]]<docommand="new_command"|script="new_script"><step=step><sameworkstation=><noask>
You must provide a job name which is a mandatory parameter to run the command. All
the other parameters are optional. The details required with each parameters are as
follows:Specify the job to update, by means of attributes and qualifiers.
from=[[folder/]wkstat#]job- wkstat#
You can specify the name of the workstation on which you want to run the job.
- jobYou can specify the name of the job that you want to run.Restriction: The following types are not permitted:
- The jobs submitted using the submit docommand.
- The alias names of jobs submitted using the submit job command.
recovery option | from intial job | Retrieved from "from" job |
---|---|---|
stop | No | Yes |
You can specify the start time for the rerun as follows:
hhmm [timezone|tz tzname] [+n days | date]
hhmm: Specify the hour and minute.+n days: Specify the next occurrence of rerun in number of days.
date: Specify the date for the next occurrence of rerun in mm/dd/yy.
timezone|tz name: Specify the timezone. For valid time zones, see Managing time zones.
streamlogo|logon=new_logonYou can use the option to run the job under a new user name. The option is only applicable for completed jobs. The option is mutually exclusive with from, script and docommand.
docommand="new_command"You can specify new command to rerun the jobs instead of original command. The option is only applicable for completed jobs. The option is mutually exclusive with script and from.
script="new_script"You can specify new script to rerun the jobs instead of original script. The option is only applicable for completed jobs. The option is mutually exclusive with docommand and from.
noaskWhen you add the option as an argument the agent will not ask for confirmation before taking action on each qualifying job.
Examples
- To rerun job
job4
in job streamsked1
on workstationmain
, run the following command:ocli plan rr main#sked1.job4
- To rerun job
job5
in job streamsked2
using the job definition for jobjobx