Removing an operation from the current plan and restoring it
To remove (NOP) an operation that is already in the current plan, enter the NP command beside the row in the ready list. NP can be issued for any operation on the ready list that has status A, R, *, W, or (for computer workstations with automatic reporting only) C.
The scheduler processes status changes for NOP operations until they reach a status of A, R, or * (ready). The scheduler ignores time dependency, use of special resources, and other constraints. When a NOP operation reaches the ready status A, R, or *, HCL Workload Automation for Z immediately sets the operation to status C; the operation is not submitted, and successor operations are eligible to start. NOP operations are identified by the N extended status code.
If you want to restore the operation, use the UN command. The UN command does not affect the status of the operation. It merely removes its NOP characteristics. The operation can be treated as any normal operation on the ready list.
The NP command gives to the operation the property NOP. This property can be removed from the operation by the UN command only. Neither the NP command nor the UN command changes the status of an operation directly. A NOP operation is automatically changed to completed status when it reaches ready status, regardless of whether other constraints are met.
Use the MCP panel for an operation that is not on the ready list. See Modifying operations for more details.
- The value set in the associated run cycle, if applicable.
- The value set in the Application Description database.
- The value overwritten by the user when the operation is added to the CP (from the ISPF panel).