To make a baseline for a set of activities

Procedure

  1. Ensure that the stream is locked.
  2. In the Project Explorer, select the integration stream or feature-specific development stream in which you want to make the baseline.
  3. Click Tools > Make Baseline.
    The Make Baseline window opens.
  4. If the project does not have a baseline naming template set or the template includes the basename token, enter a name in the Baseline Title (Linux and the UNIX system) or Base Name (Windows systems) field.
    The Template Name field shows the name that will be used for the new baseline if a baseline naming template is set for the project. If a baseline naming template is not set for the project, the Base Name or Baseline Title field does not appear in the Make Baseline window.
  5. Click Activities in the Make Baseline window, and select the activities that you want to go into the baseline.
  6. Click General and select the type of baseline to create.
  7. Specify a view in which to perform the operation. Choose a view that is attached to the stream where you want to make the baseline.