If your
project team works on multiple components, you may want to use a composite
baseline. A composite baseline selects baselines in other components
(see Composite baseline). Figure 1: Composite baseline
The PB1 composite baseline selects baselines BL1 and BL2 of
components A and B, respectively. The Proj component
does not contain any elements of its own. It contains only the composite baseline
that selects the recommended baselines of the project components. By using
a composite baseline in this manner, you can identify one baseline to represent
multiple baselines, and, by extension, the entire project.