Modifying phase to specify current iteration

About this task

As your project proceeds through its timeline, one iteration will complete and the next iteration of work will commence. You can keep track of which iteration is the current iteration for a phase by specifying Current® Iteration on the ALMPhase record. You can specify which Phase is the Current Phase on the ALMProject record.

Procedure

  1. In the HCL Compass client Navigator view, navigate to the Public Queries > ALM > Generic folder and double-click the All Phase query to run it.
  2. Select the phase that you previously created from the Query Results grid.
  3. Click the Modify toolbar icon.
  4. Select the label for the iteration you previously created in the Current Iteration Label field.
  5. Click OK.