When the scheduler evaluates the status of a condition dependency

The status of condition dependencies and, consequently, the status of the condition to which they belong, is evaluated when the conditional predecessor has one of the following statuses:
S
Started
E
Ended in Error
C
Completed
X
Suppressed by Condition
or when a step-end event is received.

The condition dependency is evaluated only when a path in the plan exists, otherwise the condition dependency remains Undefined until a manual intervention or a Rerun is done.

A possible path for the conditional predecessor exists when at least one of the following conditions occurs:
  • The job is set to C and a normal successor exists.
  • There is at least one conditional successor that has all the subsets of conditions referencing that conditional predecessor true according to the condition rules.