Running the scenario

About this task

After you updated your current plan, you can monitor your critical workload by using the QCP dialog:
  1. 1. Select the CRITICAL JOB option. The following list is displayed, showing that the Risk Level (RL) for the DBSTART job is Potential risk:
    Figure 1. EQQSCJOB - Browsing critical jobs
    EQQSCJOB -----------– BROWSING CRITICAL JOBS (left part) -—-- Row 1 to 2 of 2
    
    Command ===>                                                 Scroll ===> CSR
    
    Enter any of the row commands below
     S - critical path             H - critical hot list
    Press ENTER to refresh.
    
    Row  Application id   Operation Jobname  Input Arrival   Deadline        RL  S  R 
    cmd                   ws   no.           Date     Time   Date     Time            
    '''' DBAPPL1          CPU1 003  DBPRINT  08/02/15 14.55  08/02/15 15.00  N   W  P 
    '''' DBAPPL1          CPU1 004  DBSTART  08/02/15 14.55  08/02/15 15.00  P   W  P 
    ********************************* Bottom of data *******************************
  2. Select the DBSTART job and enter the critical hot list (H) row command. The displayed panel shows that the L column is set to Y in the Flags field, meaning that DBMAINT is a late job:
    Figure 2. EQQSCP1L - Browsing critical hot list (left part)
    EQQSCP1L ------- BROWSING CRITICAL HOT LIST (left part) --- Row 1 to 1 of 1 
    
    Command ===>                                                  Scroll ===> CSR   
    Application           :  DBAPPL1                                                
    Operation             :  CPU1 4                                                 
    WLM Class and Policy  :                                                         
                                                                                    
    Enter the row command S to select an operation for details.                     
    Press ENTER to refresh.                                                         
                                                                                    
    cmd                   ws    no.           U W    L R         start     arrival  
    '''' DBAPPL2          CPU2  001 DBMAINT   N N    Y N     A 5  15 06.58  15 06.00
    ******************************* Bottom of data *********************************
  3. Check the status of the CPU2 workstation. It is offline.
  4. Activate the workstation. The DBMAINT job starts to run.
  5. Return to the BROWSING ACTIVE CRITICAL JOBS panel. The refreshed list shows that the Risk Level (RL) for the DBSTART job is now No risk.
    Figure 3. EQQSCJOB - Browsing active critical jobs (left part)
    EQQSCJOB ----- BROWSING ACTIVE CRITICAL JOBS (left part)-—- Row 1 to 2 of 2 
     Command ===>                                                  Scroll ===> CSR  
                                                                                    
     Enter any of the row commands below:                                           
      S  - critical path            H  - critical hot list                          
     Press ENTER to refresh.                                                        
                                                                                    
     Row  Application id   Operation  Jobname  Input Arrival  Deadline       RL S R 
     cmd                   ws     no.          Date     Time  Date     Time         
     '''' DBAPPL1          CPU1   003 DBPRINT  08/02/15 14.55 08/02/15 15.00 N  W P 
     '''' DBAPPL1          CPU1   004 DBSTART  08/02/15 14.55 08/02/15 15.00 N  W P 
     ******************************* Bottom of data ********************************