Keeping plans up-to-date
About this task
When you have changed the current plan, or when the duration of
some work has varied significantly from its schedule, the planned
times in the current schedule might be inaccurate. To make HCL Workload Automation for Z recalculate
these times, taking the current information into account, replan the
current plan. You can do this in two ways:
- Enter the Replan panel from the DAILY PLANNING panel, by selecting the 1 (REPLAN) option on the PRODUCING OPC DAILY PLANS panel. The scheduler will then submit the replan job.
- Define the replan job as an application in HCL Workload Automation for Z so you can schedule the replan as you would any other application, and HCL Workload Automation for Z will submit it automatically.
The REPLAN job removes all completed occurrences from the current plan panels.