Taking action at the occurrence level
About this task
If the operation cannot be restarted because you
need to change the application occurrence, perform the following steps:
- In the MODIFYING OCCURRENCES IN THE CURRENT PLAN panel (option 5.2), enter the M row command beside the occurrence. The MODIFYING AN OCCURRENCE IN THE PLAN panel is displayed.
- Change the occurrence, as necessary.
- In the MODIFYING OCCURRENCES IN THE CURRENT PLAN panel, enter the R row command to rerun the occurrence. The RERUNNING AN OCCURRENCE IN THE CURRENT PLAN panel is displayed.
- Enter the S row command to set the start point.
- Issue the RC command, if needed.
Alternatively, you can directly rerun the occurrence without making modifications. Use the R row command in the MODIFYING OCCURRENCES IN THE CURRENT PLAN panel, performing steps 3 to 5.