Operation priority
If there is more than one operation that can be started,
the WA scheduler selects an operation by investigating these characteristics
in the stated order:
- Priority 9.
- Earlier latest-start time.
The latest-start time is calculated internally by HCL Workload Automation for Z, and is the latest time (based on the operation duration) that the operation must start if it is to be completed before its deadline. If no deadline is specified for the operation,HCL Workload Automation for Z uses the occurrence deadline and subtracts the duration for each successor operation on the critical path.
- Priority 8–1.
- Shortest estimated duration.
- First-in first-out basis.