RESOURCE
Purpose
The RESOURCE statement identifies the special resources for which the reports are required. You can specify more than one RESOURCE statement. RESOURCE statements are used when a daily planning job requests special resource reporting. A special resource is included in a report if it exists and if its name matches a value on a RESOURCE statement. If you do not specify RESOURCE, no reports are produced.
You specify RESOURCE statements in the member of the parameter library that contains the BATCHOPT statement.
Format
Parameters
- FILTER(special resource name,...,special resource name)
- FILTER values identify special resources
that HCL Workload Automation for Z includes
when planned or actual resource-utilization reports are requested
by a daily planning job. Each value is compared with special resources
known at planning time. If a special resource name matches a filter
value, it is reported on. A special resource is selected only once
if it matches more than one filter value, even if the values are on
different RESOURCE statements. Each value is 1–44 characters
and must not contain embedded blanks.
You can specify asterisk (*) and percent (%) anywhere in a value. An asterisk matches any character and any number of characters. A percent sign matches any 1 character.
In this example of RESOURCE statements, reports are generated for special resources whose
names contain:
- 1
- TAPE as the first 4 characters followed by any number of characters, and 34 as the first 2 characters followed by 2 more characters.
- 2
- 80 as the last or only characters.