To move versions to a different activity

Procedure

  1. Display the properties of an activity. For example, do the following:
    1. Start the Project Explorer. If you are using a Windows system, start the Project Explorer by doing the following: in HCL VersionVault Windows Explorer, click Toolbox and then click UCM > Project Explorer.
    2. In the Project Explorer left pane, select the stream that contains the activity.
    3. In the right pane, right-click the activity and then click Properties.
  2. In the Properties window, perform one of the following actions:
    • Click the Change Set tab.
  3. Right-click a version, and then click Move to Activity.
  4. In the Select Activity window, select an activity and click OK.
  5. Click OK to close the Properties window.