To move work from a development stream to another project
About this task
To move work from a development stream to another project:
Procedure
- Get the activity selector of the activity.
You can do this by entering the following command in your development view:
You can also get the activity selector by doing the following:cleartool lsactivity -long -cview
- Find the activity. For example, in HCL VersionVault Windows Explorer, use MyActivities.
- Right-click the activity and on the pop-up menu,
click Properties.
On the General page in the Properties window, the ID field displays the activity selector.
- Write down the activity selector or copy it to the clipboard, and then close the Properties Browser if it is open.
- Join the project in which you intend to complete the work.
- Decide whether to add the work to the integration stream in the new project or to another development stream in the new project.
- From your view in the original project, deliver the
work that you are moving to a nondefault target (the stream in the new project
in which you intend to complete the work).
Use the activity selector from Step 2 to specify the work to be delivered.
- Lock (in the obsolete state) your development stream for the original project (see the lock reference page).
- Remove your development view for the original project.