Baseline 2 has been released internally, and further testing has found only minor bugs (see
the following figure). These bugs have been
fixed by creating new versions on the main branch. Figure 1. Final test and release
Before the monet application is shipped to customers, it goes through
a validation phase:
All editing, building, and testing is restricted to a single, shared view.
All builds are performed from sources with a particular version label
(R2.0).
Only the project manager has permission to make changes involving that
label.
All labels must be moved by hand.
Only high-priority bugs are fixed, using this procedure:
The project manager authorizes a particular developer to fix the bug,
by granting her permission to create new versions (on the main branch).
The developer’s checkin activity is tracked by anHCL
VersionVault trigger.
After the bug is fixed, the project manager moves the R2.0 version
label to the fixed version and revokes the developer’s permission to create
new versions.