Planning the Unica Plan upgrade
For upgrading to Unica Plan 12.1.2 version, you must check from which version you are upgrading. Upgrade scenarios are based on the current version of the Unica Plan.
Unica Plan supports the following upgrade paths:
- 12.1.x → 12.1.2
- 12.1.0.x → 12.1.2
Customers on versions earlier than 8.6.x must:
- perform a Fast Upgrade from existing version to version 8.6.0 (for more information, see HCL Unica 8.6.0 Fast Upgrade Guide).
- perform a Fast Upgrade from version 8.6.0 to version 12.1.0 (for more information, see HCL Unica 12.1.0 Fast Upgrade Guide).
- perform an in-place upgrade from version 12.1.0 to version 12.1.2.
Customers on versions earlier than 11.1.x.x can:
- perform a Fast Upgrade from existing version to version 12.1.0 (for more information, see HCL Unica 12.1.0 Fast Upgrade Guide).
- perform an in-place upgrade from version 12.1.0 to version 12.1.2.
Customers on versions 11.1.x.x/12.0.x.x can use one of the following options for upgrade:
- Option 1
- perform an in-place upgrade from existing version to version 12.1.0.
- perform an in-place upgrade from version 12.1.0 to version 12.1.2.
- Option 2
- perform a Fast Upgrade from existing version to version 12.1.0 (for more information, see HCL Unica 12.1.0 Fast Upgrade Guide).
- perform an in-place upgrade from version 12.1.0 to verison 12.1.2.