Unica Plan | umoConfiguration | workflow
These properties specify options for the workflow in Unica Plan.
hideDetailedDateTime
- Description
-
Optional show/hide parameter for detailed date time in the tasks page.
- Valid values
True | False
- Default value
False
daysInPastRecentTask
- Description
-
This parameter determines how long tasks are considered "recent." If the task is "active" and started less than this number of days ago, or the Target End Date of the task is between today and this number of days in the past, the task displays as a recent task.
- Valid values
positive integers
- Default value
-
14 (days)
daysInFutureUpcomingTasks
- Description
-
This parameter determines how many days in the future to look for upcoming tasks. If the task starts in the next daysInFutureUpcomingTasks or does not end before the current date, it is an upcoming task.
- Valid values
positive integers
- Default value
-
14 (days)
beginningOfDay
- Description
-
Begin hour of the working day. This parameter is used to calculate the datetimes in workflow using fractional durations.
- Valid values
integers from 0 to 12
- Default value
-
9 (9 AM)
numberOfHoursPerDay
- Description
-
Number of hours per day. This parameter is used to calculate the datetimes in workflow using fractional durations.
- Valid values
integers from 1 to 24
- Default value
-
8 (hours)
mileStoneRowBGColor
- Description
Defines the background color for workflow tasks. To specify the value, insert the # character before the six-character Hex code for the color. For example, #0099CC.
- Default value
-
#DDDDDD
UI
- Description
- Defines the version of the workflow UI. The possible values are Enhanced to show the modern UI, or Classic to show UI as in version before 12.1. This is a system-level setting and not a user-level setting or project-level setting. If you modify this setting, you must restart the Plan application.
- Default value
- Enhanced