The Domino® administrator
can specify when Domino Attachment
and Object Service (DAOS) resynchronization should run on a server,
so that peak production hours can be avoided.
About this task
If you do not want to schedule a specific time for resynchronization
by using a Program document (see the related information for a wiki
article on how to do that), you can set up a time window to specify
whether or not resynchronization may run at a given time, and also
tell it to stop at a specified stop time. For more details, see the
time window technote under related information.
Procedure
- On the Domino server
where DAOS is enabled, edit the NOTES.INI file.
- Add the following parameters and values. The format of
the time is as follows:
HH:MM:SS AM/PM
.DAOS_RESYNC_START_TIME=time
DAOS_RESYNC_STOP_TIME=time
For example:
DAOS_RESYNC_START_TIME=12:00:00 AM
DAOS_RESYNC_STOP_TIME=04:00:00 AM