Importing an existing compound test into a project

You can import a compound test into a project.

Procedure

  1. Open the UI Test perspective in Test UI, if it is not already open.
  2. Right-click the project into which you want to import the compound test and click Import in the Test Navigator pane.
    The Import dialog is displayed.
  3. Expand Test in the source list, select Import test assets with dependencies, and then click Next.
  4. Click Browse to specify the directory in which the compound test resides.
    The compound test assets in the folder you selected are displayed. By default, the compound test is imported into the project folder.
  5. Select the components you want to import.
  6. Click Finish.
    The imported compound test is displayed in the Compound Test Elements panel in the Compound Test editor.