for-each-agent
The for-each-agent application process step lets you run a process for each agent in an environment.
Format
for-each-agent step "loop1" is
-- define target resource tags; optional, repeatable
-- before 7.1.1.0, the tag must be specified by internal database ID
tag "res-tag-1"
tag "res-tag-2"
-- maximum number of agents to target concurrently; optional
-- default is unlimited
max-concurrent-agents unlimited
-- must contain an embedded 'start' block that works like the top-level version
start is
start "install-c1"
end
-- contains one or more embedded steps of any type except for other for-each steps
install-component step "install-c1" is
component "c1"
process "deploy"
without-status "Active"
fail-fast true
ignore-child-warnings true
max-concurent-processes 43
-- on success/failure/complete reference steps inside the for-each
-- 'finish' refers to the implied finish step inside the for-each
on success
finish
end
-- on success/failure/complete outside an embedded step reference steps in the top-level process
on success
start "next-step"
end
Properties
Field | Description |
---|---|
Name | A name for the iteration container. |
Limit to Resource Tags | A list of resource tags that limit the container. The subprocess runs only on the agent resources that have one or more of the specified resource tags. |
Maximum number of concurrent processes | The maximum number of agents that run the
subprocess at a time. To run the subprocess on every agent at once, specify
-1 . To limit the number of agents to deploy to at once, as in
blue/green deployments or rolling deployments, specify an integer. The server attempts to resolve the value to an integer. If the value does
not resolve to an integer, then the |
Example
start is
start A
start B
end
for-each-agent step A is
tag "res-tag-a1"
tag "res-tag-a2"
tag "res-tag-a3"
max-concurrent-agents 42
start is
start A1
end
set-final-process-status step A1 is
status success
on success
finish
end
on complete
finish
end
for-each-agent step B is
start is
start B1
end
set-final-process-status step B1 is
status success
on success
finish
end
on complete
finish
end