Create a testing stream is shown as a workflow of the project integrator. It is first in the workflow and precedes Build components.

In your role as project integrator, you are responsible for building the work delivered by developers, creating baselines, and testing those baselines. When you make baselines in the integration stream, you lock the stream to prevent developers from delivering work. This practice ensures that you work with a static set of files. It is acceptable to perform quick validation tests of the new baselines in the integration stream. However, you should not lock the integration stream for a long time because you will create a backlog of deliveries. To perform more rigorous testing, such as regression testing, you should create a development stream to be used solely for stabilizing and testing baselines.