Creating phase
About this task
The ALMPhase record is associated with a project and specifies for the project how the project timeline will be grouped into larger tracking units. The phase can also be used to track work for Milestones. If the project is only being tracked by iterations, then you can configure only one phase label, and name it Iteration. The iteration labels could then be iteration numbers. The mandatory fields are Project, SecurityPolicy, and PhaseLabel. The Prior Phase field is optional.
Procedure
- In the HCL Compass client, click .
- Select the phase label that you previously created in the PhaseLabel field. Click Add next to the Project field. Either enter a keyword and click Search or click Browse and navigate to a query to run to return a list of projects. Select the project to be associated with this phase and click OK.
- Click OK.