To create a project based on an existing project
Procedure
- Start the New Project Wizard to create the project.
- In Step 2 of the wizard, set Yes.
This indicates that the project begins from the baselines in
an existing project.
- Then navigate to the project that contains those baselines.
For example, the new project is based on the baselines in the OM_proj1.0_Integration stream.
- Step 3 lists the latest baselines in the project that you
select in Step 2.
- If you created a pure composite baseline to capture the final
approved baselines in the existing project, select it.
- Click Add to add baselines from components
that are not part of the existing project. The Add Baseline window
opens.
- Remove a baseline by selecting it and clicking Remove.
- Finish the remaining steps in the wizard.