To fix a problem in a new baseline
Procedure
- From the development view attached to the development
stream, specify an activity and check out the files that you need to fix.
- Make the necessary changes to the files and check them in.
- Build and test the changes in the development view.
- When you are confident that the changes work, make a new baseline
that incorporates the changes in the development stream.
- Deliver the new baseline to the integration or feature-specific
development stream.
When you deliver the new baseline to the integration
or feature-specific development stream, you merge changes with work that developers
have delivered since the last baseline was created.
- Change the set of recommended baselines for the integration stream
or feature-specific development stream to include the new baseline that you
made in the testing stream.