Creating the Bandwidth Manager cluster
Create the cluster configuration for an IBM® Sametime® Bandwidth Manager cluster. The two application servers that were just installed need to be clustered together before installing the Sametime Bandwidth Manager software. Ensure that the Deployment Manager is running as well as the node agent on each application server. Services are not created for the node agents, so they are started manually. We will also create services for them in a later step.
About this task
Create the cluster on the computer hosting the deployment manager.
Procedure
- Start the deployment manager:
- Start each application server's node agent:
- Log in to the Integrated Solutions Console as the WebSphere® administrator.
- On the navigation tree, click .
- On the clusters page, click the New button at the beginning of the table.
- On the Create a new cluster page, type a descriptive name for the cluster (for example, BWMcluster).
- Click Configure HTTP session memory-to-memory replication. Click Next.
- On the Create first cluster member page, type a descriptive name for the first cluster member (for example, BWMserver1). In the Select node field, select the first Bandwidth Manager server node. Click Next.
- On the Create additional cluster members page, add a second
cluster member by completing these steps:
- In the Member name field, enter a cluster member name, for example, BWMserver2.
- In the Select node field, ensure that the second Bandwidth Manager server is selected.
- Click Add Member.
- Ensure that you see both cluster members in the Member name and the Node fields in the table, and then click Next.
- Review the summary information to ensure that each server name coordinates to a unique node name. Click Finish.
- Click the Save link in the "Messages" box at the beginning of the page.
- Synchronize all nodes in the cluster by completing these
steps:
- From the Integrated Solutions Console, click .
- Select all of the nodes in the cluster.
- Click Full Resynchronize.
- Restart the node agents from the Integrated Solutions Console
by completing these steps:
- Click .
- Select each node agent in the table. and then click Restart.
- Click the Status icon to refresh. When the node agents are green, proceed to the next step.
- Select the cluster and click Start to start all cluster member servers.