Disassociating a functional test project from a Rational project
If you no longer want to associate a functional test project to a Rational® project, you can disassociate it from a Rational® project.
About this task
When you disassociate a project from the current Rational® project:
- You cannot play back Functional Test scripts, test cases, or suites that include Functional Test scripts in the disassociated project from TestManager.
- TestManager deletes the test script source from the disassociated project.
- You cannot undo this operation. If you associate the Functional Test project with a Rational® project again, TestManager creates a new test script source. For information about TestManager, see the Rational® TestManager Help.
To disassociate a Functional Test project from a Rational® project:
Procedure
- Start HCL OneTest™ UI and log in to the Rational® project.
- In the Solution Explorer, right-click the Functional Test project
and click Disassociate from current Rational Project.
This menu item is available only if you have administrative privileges with the project.
- Click Yes.
HCL OneTest™ UI removes the name of the Rational® project that you associated with a Functional Test project from the Functional Test project in the Solution Explorer.