To fix a problem in a new baseline

Procedure

  1. From the development view attached to the development stream, specify an activity and check out the files that you need to fix.
  2. Make the necessary changes to the files and check them in.
  3. Build and test the changes in the development view.
  4. When you are confident that the changes work, make a new baseline that incorporates the changes in the development stream.
  5. Deliver the new baseline to the integration or feature-specific development stream.
    When you deliver the new baseline to the integration or feature-specific development stream, you merge changes with work that developers have delivered since the last baseline was created.