Stream hierarchies
The project manager created a development stream called Permissions_dev for two developers who are working on a permissions feature. The developers, Pat and Pedro, joined the project at the Permissions_dev level rather than at the integration stream level. They deliver completed work to the Permissions_dev stream. Periodically, the integrator or lead developer responsible for managing the Permissions_dev stream incorporates the delivered work into new baselines, and the developers rebase their development streams to those new baselines.
When the two developers finish working on the permissions feature, they deliver their last work to the Permissions_dev stream. The integrator incorporates their delivered work into a final set of baselines and delivers those baselines to the integration stream.